May 28, 2003 (morning)
 

 

First thing Wednesday morning the trucks arrived bringing gravel for under the concrete slabs and the sand & gravel for the field drain.

 


 

After a while the Idaho Power backhoe driver arrived. Here he is waiting for the other workers to arrive so they could begin placing the conduit in the trench. Below they are finally getting underway.

 

 


 

 

Meanwhile Mike F. was busy laying in and burying all the water and sewer lines as well as the power line that will run to the house from the point where Idaho Power will stop at the transformer. He just flies along on that backhoe!!

 


 

 

And when he was finished with that, he backfilled more of the foudation stem walls. He has to wait to completely finish them up until the cement workers show up to fix the misplaced footing.


 