Page Eighty-Six
July 11, 2003
 

 

When the insulation crew arrived on Friday, they began getting the ceilings ready for the blown in insulation.

 

After padding the pipes in the kitchen ceiling, they began stapling up this light-weight fabric everywhere the blown in insulation would go.

 

 

 


 

 

Martin also went around filling the areas above all the doors and windows with insulation.

 

Then he went upstairs and began filling each section between the trusses with the foam.

 

Some of the channels had these paper rulers (shown below) stapled in so he could keep track of the depth of insulation.

 


 