May 20, 2003
Foundation Footing Forms
Today was the day for building
the forms for the foundation footings. We also picked up our sewage system
and building permits. Our building permit also informed us of our new address.
After we move to our new house, our address will no longer be 4390, it will
now be 4301! |
|
|
|
Bright and early Tuesday morning brought the crew from Ryan Lowe Construction to build the forms for the foundation footings. |
||
|
|
|
|
|
This set of photos show the rebar being placed in the forms. |
||
|
|
|
The photo below shows the completed form ready for inspection tomorrow. Then we just wait for the concrete trucks to begin pouring! |
||
|