Site Map
 

Home Page

Special Thanks & Photos

Details & Floor Plans

Date

Location

Event

April 28, 2003

Page   1

Work Begins

May 1, 2003

Page   2

Driveway

 

Page   3

Foundation Markers
Driveway

May 1, 2003

Page   4

(text only)

May 15, 2003

Page   5

Closing Day

May 17, 2003

Page   6

The Big Dig

May 19, 2003

Page   7

Septic Test Hole

May 20, 2003 

Page   8

Foundation Footing Forms

May 21, 2003

Page   9

Foundation Footings

 

Page 10

Tree Berm

May 22, 2003

Page 11

Footing Forms Removed

May 23, 2003

Page 12

Stem Wall Forms

 

Page 13

Stem Walls

May 24, 2003

Page 14

Stem Wall Forms Removed

May 27, 2003

Page 15

Utility Trenches

 

Page 16

Stem Wall Backfill

May 28, 2003

Page 17

Utility Trenches (cont)

 

Page 18

Utility Trenches (cont)

May 29, 2003

Page 19

Power Line Road Bore

 

Page 20

Septic Tank Install

 

Page 21

Utility Trenches (cont)

May 30, 2003

Page 22

Compacting Backfill
Drain Field

 

Page 23

Prepping Garage Floor
Power Line

June 2, 2003

Page 24

Transformer
Drain Field
Footing Repair

 

Page 25

Flatwork Prep
Lumber Arrives

June 4, 2003

Page 26

Final Septic Inspection

June 5, 2003

Page 27

Drain Field Filled In

June 6, 2003

Page 28

Flatwork

 

Page 29

Flatwork (cont)

 

Page 30

Septic Tank Filled In
Porch Post Footing

 

Page 31

Driveway Culverts

June 9, 2003

Page 32

Framing Begins

 

Page 33

Framing (cont.)

 

Page 34

Power Hook-up
More Supplies

 

Page 35

Driveway

June 10, 2003

Page 36

Framing (cont.)

 

Page 37

Flatwork (cont)

 

Page 38

Roadwork
Misc

June 11, 2003

Page 39

Walls

 

Page 40

Walls (cont.)

 

Page 41

Roadwork
Misc

June 12, 2003

Page 42

More Walls

 

Page 43

More Walls (cont)

 

Page 44

The Rock

 

Page 45

The Rock (pt. 2)

 

Page 46

Supplies

June 13, 2003

Page 47

Framing (upstairs)

 

Page 48

Framing (cont.)

June 14, 2003

Page 49

Misc Views

June 16, 2003

Page 50

Trusses

 

Page 51

Trusses (cont.)

 

Page 52

Trusses (cont.)

 

Page 53

Misc Views

June 17, 2003

Page 54

Trusses (cont.)

June 18, 2003

Page 55

Framing (cont.)

 

Page 56

Walk-About Views

June 19, 2003

Page 57

Plumbing

 

Page 58

Misc.

June 20, 2003

Page 59

A Hard Rain

June 21, 2003

Page 60

Dry Sheeting

 

Page 61

Misc.

June 23, 2003

Page 62

Heating/Cooling

 

Page 63

Heating/Cooling (cont.)

 

Page 64

Plumbing (cont.)

June 24, 2003

Page 65

Shower Units

June 25, 2003

Page 66

House Wrap

 

Page 67

Doors & Windows Prep

 

Page 68

Plumbing (cont.)

June 26, 2003

Page 69

Garden Tub

 

Page 70

Windows Arrive

 

Page 71

Windows

 

Page 72

Misc.

June 27, 2003

Page 73

Windows

 

Page 74

Misc.

June 30, 2003

Page 75

Siding

 

Page 76

Electrical

 

Page 77

Misc.

July 2, 2003

Page 78

Siding (cont.)

July 3, 2003

Page 79

Electrical Inspection
Siding (cont.)

July 8, 2003

Page 80

Framing Inspection
Under House Views

July 8-9, 2003

Page 81

Cable, Phone and
Internet Wiring

July 10, 2003

Page 82

Insulation

 

Page 83

Insulation (cont.)

 

Page 84

Misc.

 

Page 85

Misc.

July 11, 2003

Page 86

Insulation (cont.)

 

Page 87

Insulation (cont.)
Misc.

July 15, 2003

Page 88

Sheetrock Delivery

July 16, 2003

Page 89

Sheetrock

 

Page 90

Sheetrock (cont.)

 

Page 91

Sheetrock (cont.)

 

Page 92

Siding (cont.)
Insulation (cont.)

July 17, 2003

Page 93

Sheetrock (Final)

July 18, 2003

Page 94

Tape & Mud

 

Page 95

Tape & Mud (cont.)

 

Page 96

Siding (cont.)
Misc.

July 19-20, 2003

Page 97

Circle Driveway Rocks

 

Page 98

Driveway Rocks (cont.)

July 21, 2003

Page 99

Well Drilling

 

Page 100

Well Drilling (cont.)

 

Page 101

Tape & Mud (cont.)

 

Page 102

Heating/Cooling (cont.)
Transformer

July 22, 2003

Page 103

Well Drilling (cont.)

 

Page 104

Well Drilling (cont.)

 

Page 105

Well Drilling (cont.)

July 23, 2003

Page 106

Roof Flashing
Siding (cont.)
Wall & Ceiling Texture

July 24, 2003

Page 107

Texture (cont.)

 

Page 108

Siding (cont.)
Misc.

July 25, 2003

Page 109

Rain Leak

 

Page 110

Ext. Painting

 

Page 111

Int. Doors & Trim Arrive

 

Page 112

More Rain

July 26, 2003

Page 113

Window & Door Trim

 

Page 114

Win. & Door Trim (cont.)
Rain Again

July 28, 2003

Page 115

Win. & Door Trim (cont.)

 

Page 116

Ext. Painting (cont.)

July 29, 2003

Page 117

Int. Paint Prep
Ext Doors

July 30, 2003

Page 118

Pump & Water Lines

 

Page 119

Pump & Water
Lines (cont.)

 

Page 120

Pump & Water
Lines (cont.)

 

Page 121

Pump & Water
Lines (cont.)

 

Page 122

Shelves, Int. Trim
and Ext Doors

 

Page 123

Porch Railing
Ext. Paint Trim (cont.)

July 31, 2003

Page 124

Garage Doors

 

Page 125

Interior Paint Prep
Cabinet Measurements

August 1, 2003

Page 126

Interior Paint Prep

 

Page 127

Power Connect
Porch Railing

August 3, 2003

Page 128

Interior Paint
Porch Railing

August 4, 2003

Page 129

Roofing
Paint (cont.)

August 6-9, 2003

Page 130

Roofing (cont.)
Pre Cabinets &
Stair Railing

August 10, 2003

Page 131

Ext. Progress Views

August 11, 2003

Page 132

Stair Railing (cont.)

 

Page 133

Roofing (cont.)
Misc.

August 12, 2003

Page 134

Stair Railing (cont.)
Floor Sanding

 

Page 135

Road Oiling

August 13, 2003

Page 136

Painting (cont.)

 

Page 137

Stair Railing (cont.)
Stonework (prep.)

August 14, 2003

Page 138

Vinyl Installation

 

Page 139

Vinyl Flooring (cont.)

 

Page 140

Stair Railing (cont.)
Painting (cont.)

August 15, 2003

Page 141

Deck Material
Roofing (Ridge Vents)

 

Page 142

Vinyl Flooring (cont.)

August 18, 2003

Page 143

Carpet Installation

 

Page 144

Carpet (cont.)

August 21, 2003

Page 145

Cabinets

 

Page 146

Cabinets (cont.)

August 22, 2003

Page 147

Pressure Tank
Misc.

August 23, 2003

Page 148

Counter Top Laminate

August 26-28, 2003

Page 149

Laminate (cont.)
Plumbing Fixtures

 

Page 150

Deck Construction

 

Page 151

Master Bath Vanity Fix

August 29, 2003

Page 152

Exterior Stone Work

 

Page 153

Electrical (cont.)

 

Page 154

Deck (cont.)
Finish Trim (cont.)

September 2, 2003

Page 155

Electrical (cont.)

 

Page 156

Plumbing (cont.)

 

Page 157

Deck (cont.)
Paint (cont.)
Misc.

September 3, 2003

Page 158

Heating/Cooling (cont.)
Appliances

 

Page 159

Deck (cont.)
Plumbing (cont.)

September 4, 2003

Page 160

Electrical (cont.)

 

Page 161

Stair Railings (cont.)

 

Page 162

Deck (cont.)
Misc.

September 8, 2003

Page 163

Furnace Installation
Sheetrock Repairs
New Stove

September 10, 2003

Page 164

Phone Line (cont.)
Plumbing Insp. Prep.

September 11, 2003

Page 165

Furnace
Plumbing Insp.

September 14, 2003

Page 166

Rock (cont.)
Cable Prep

September 15, 2003

Page 167

Landscaping
Final Paint

September 16, 2003

Page 168

Landscaping (cont.)

September 17, 2003

Page 169

Landscaping (cont.)
Stonework (below)
Furnace Wiring

September 18, 2003

Page 170

Rain Gutters

September 18, 2003

Page 171

Landscaping (cont.)

September 18, 2003

Page 172

Electrical (final)

September 19, 2003

Page 173

Bathroom Glass

September 22, 2003

Page 174

Garage Apron &
Front Sidewalk

September 22, 2003

Page 175

Electrical Inspection
Cable Line

September 24, 2003

Page 176

Final Inspection and
Certificate of Occupancy!
Landscaping (cont.)

September 26, 2003

Page 177

Landscaping - (cont.)
(Sod placement)

September 27, 2003

Page 178
(Final Page)

Open House Preparation
Final Views

< Home Page >